Salem City Seeks Bids for New Water Line to K-8 School District Building

More than 2,000 feet of new water line will soon connect to the Salem City School District’s new K-8 school building, with city leaders moving forward to advertise for construction bids.

City council voted on Tuesday to approve an ordinance authorizing the utilities department to seek bids and enter into contracts for the installation of a 12-inch main water line. Utilities Superintendent Chad Hess explained that the project will begin on Pershing Street near Giant Eagle and join with the school’s existing lines on Merle Road.

The city and the school district will split the costs of engineering and the main line installation down the middle. During the Salem school board’s Nov. 9 meeting, Treasurer Mike Douglas pointed out that the new pipe was required to guarantee an adequate gallons-per-minute supply for firefighters to utilize if a blaze breaks out on the site.

Although construction costs are being split, the municipality will pay entirely to link dead end streets along the path to the fresh main in order to preserve water circulation. Hess told the utilities commission on Thursday that plans for the water line had received approval to begin construction from the Ohio Environmental Protection Agency.

Hess said that preparations involve securing property rights along the route. He said that an agreement for one of three necessary easements with intermediary property owners had been completed after he picked up the paperwork from City Law Director Brooke Zellers on Tuesday.

“I picked it up from Zellers Tuesday night, so I just have to get that filed with the county.”

Hess told the utilities commission. He added that he was working with another property owner to finalize a second agreement, while a third agreement pended the finalization of a property sale.

With the Salem Board of Education approving the cost-sharing agreement during its Nov. 9 meeting, paperwork between the district and the city remains nearly complete. Hess said that finalizing those details involves meeting with the administration to sign the agreement and get their two easements filed as well. Construction on the project is scheduled to begin in March.