Three underground coal mines in southern West Virginia are on track to start producing metallurgical coal by early 2027, a coordinated expansion by two companies betting on steel demand rather than power-plant fuel.
Clinch Resources Ltd. announced November 16 that Underground Mine No. 8, near Gilbert in Mingo County, is fully staffed with its conveyor system installed and expected to begin production before year-end. A sister operation, Underground Mine No. 3, sits across the road next to the Hampton Prep Plant and is slated for the first quarter of 2027.
Earlier company projections put each mine at 40,000 to 50,000 tons monthly once fully operational. Meanwhile, Ramaco Resources said November 3 that its new underground mine at the Maben Complex in Wyoming County would start in December 2026, ahead of schedule, after initial development coal was extracted in late October.
“For fiscal year 2027, the company anticipates fully ramped up production across its existing mining assets of 2.4 million tons, with associated costs projected between $85 and $90 per ton,” Clinch CEO Jon Nix told shareholders on a conference call this week.
“This outlook is underpinned by three principal operational developments: the imminent commencement of production at UG Mine 8, the commencement of production at UG Mine 3 in Q1 2027, and the continued expansion of our Lanes Branch operations.”
The Lanes Branch surface mine in Wyoming County is already expanding equipment and capacity, Clinch said. A third Clinch operation, Underground Mine 6, may also open in 2027 depending on contracts and demand, though no plan is finalized. The company currently employs roughly 118 people and is not presently hiring, but expects to add crews when Mine No. 3 starts.

New Mines Target Metallurgical Coal Production
All three new mines target metallurgical coal — coking coal used in steelmaking — rather than thermal coal for electricity. Ramaco is also building a railroad loading facility at Maben, slated for completion in early 2027, which the company says could cut transportation costs by roughly $20 per ton.
Clinch reported its first quarter of coal production in the third quarter of 2026 — 43,300 clean tons generating $5.9 million in revenue — and began domestic and export sales of metallurgical coal during that period. The company said it was negotiating contracts covering more than half of its anticipated blast-furnace production and expected to secure initial specialty coal contracts by year-end.

Record rainfall and flooding disrupted Clinch’s surface production for much of August before operations returned to planned levels, the company disclosed. Both Clinch and Ramaco emphasize that projected startup dates remain subject to operational and market conditions — a standard hedge in a commodity business where steel-mill demand and global pricing can shift faster than a longwall face advances.
Ramaco noted a second underground mining section at Maben could begin as early as summer 2027, depending on market conditions. Clinch’s $85-to-$90-per-ton cost guidance for fiscal 2027 already assumes Mine No. 8, Mine No. 3, and Lanes Branch expansion all come online as planned.
Clinch Resources Ltd., a Tennessee-based metallurgical mining company with its corporate office in Knoxville, began trading on the Toronto Stock Exchange under the ticker “CLCH” on March 20, 2026. The listing followed a reverse takeover and concurrent US$46.0 million financing that included a 38.8 percent indirect acquisition of JJ Resources Inc., owner of the fully permitted 24,000-acre Sewell Mountain mid-vol metallurgical coal mine in West Virginia.
Clinch intends to use the net proceeds to develop its large met coal project, ARI, which has an estimated measured and indicated mineral resource of approximately 111 million tons of met coal over 54,000 acres, and for general working capital.
Mine No. 8 to Start Coal Before Year End
Clinch expects Mine No. 8 to start coal before December 31. Mine No. 3 follows in the first quarter. Ramaco’s Maben mine targets December 2026, with its rail loadout ready early 2027. Mine 6 remains a conditional possibility for later in 2027.