TSB Capital Arranges Financing for 12-Story Mass Timber Student Tower Across from MSU

Financing secured for The Howard, a 12-story mass-timber student tower rising across from Michigan State University, adds 707 beds to East Lansing’s tight housing market by 2028.

TSB Capital Advisors arranged senior debt and institutional equity for Harbor Bay Ventures, with Busey Bank and First National Bank of Omaha co-leading the senior loan alongside MSU Federal Credit Union and Horizon Bank’s East Lansing office, WiseVoter reported. The deal marks Harbor Bay’s first institutional equity raise, Multi-Housing News noted.

  • 707 beds, 12 stories, ~8,000 sq ft retail; pre-approved LEED Gold.
  • Nine stories of mass timber above a concrete podium — Michigan’s tallest mass-timber residential building.
  • Construction began late August 2026; completion slated for 2028.
  • Preleasing at 94.9% occupancy; average rent $872/bed.

Busey Bank, based in Champaign, Illinois, and First National Bank of Omaha, co-led the senior facility. MSU Federal Credit Union and Horizon Bank’s East Lansing office joined as local participants. TSB Capital Advisors, a Phoenix-based firm, structured the package, WiseVoter reported. Loan and equity amounts, total project cost, and terms were not disclosed by any outlet.

Screen-print poster illustration of a stepped grid of honey-toned timber beams rising from a gray concrete base under
Photo: wisevoter.com

The Howard will stack nine stories of engineered mass timber atop a concrete podium, making it the state’s tallest mass-timber residential building, according to WiseVoter. Harbor Bay Ventures previously delivered INTRO Cleveland and INTRO Columbus using the same structural system.

The firm is developing The Howard in partnership with the Ballein family, which opened the Student Book Store on the site in 1960 and previously partnered with Harbor Bay on Landmark on Grand River and Newman Lofts, Multi-Housing News reported.

East Lansing City Council approved the project on July 21, 2026. Construction started the week of August 31, 2026, the city’s construction-update page shows. A city manager’s memo noted Harbor Bay had submitted and withdrawn an earlier plan after public notice, then returned with a renewed request, Multi-Housing News reported.

Unexpectedly deep existing foundation footings may push the schedule back by up to a week, according to the city’s update page cited by Multi-Housing News.

Yardi Matrix tracked 13,626 completed student-housing beds serving MSU as of September, with preleasing at 94.9 percent — down 190 basis points from a year earlier — and average rent per bed up 3.2 percent to $872, Multi-Housing News reported. Fall 2026 enrollment reached 50,941 students, including more than 40,800 undergraduates, topping 50,000 for a fifth straight year.

Isometric editorial illustration of a single timber beam hanging from a steel crane hook in a clean, muted composition
Photo: wisevoter.com

DLR Group, the project architect, describes The Howard as a 748-bed development, while a June NAI Mid-Michigan market report called it a 15-story project, Multi-Housing News reported. The City of East Lansing’s construction-update page corroborates the 12-story figure. The discrepancies remain unresolved across available sources.

The project does not include on-site parking. East Lansing Info reported the city instead required developers to lease 224 spaces from city parking lots, Multi-Housing News noted.

“Once finished, The Howard is expected to be Downtown East Lansing’s first mass-timber structure,” the city’s project page states, per Multi-Housing News. Completion remains slated for 2028.