Unstable explosives at an Iowa plant face a controlled detonation by Tuesday despite a federal court order pausing the plan, according to court records filed late Saturday.

Court Orders and Military Plans

The government maintains that a controlled detonation is necessary to safeguard the public from the greater danger posed by an uncontrolled explosion.

On Friday, a federal court suspended the plan to detonate several tons of explosives containing lead azide at the Iowa Army Ammunition Plant in Middletown, Iowa. The 8th U.S. Circuit Court of Appeals issued an emergency order halting the demolition after environmental groups filed a lawsuit.

Lead azide detonation in Iowa by U.S. Army paused indefinitely — CBS Chicago

The Army originally scheduled two controlled explosions for Friday, then delayed them until Monday before the court stepped in. In a court filing Friday, the Environmental Protection Agency suggested the U.S. Army may proceed with detonating five tons of explosive lead azide despite the court order, KCRG reported.

Environmental Groups Challenge Army Risk Assessment

On Sunday, the Iowa Environmental Council and the Sierra Club filed a motion to supplement their emergency request to block the detonation, CBS News reported. The filing includes three expert and local government declarations that challenge the Army’s assessment of the risks of delaying the explosion.

The environmental groups also raise concerns about inadequate public notice and potential health and environmental impacts from the lead plume. Attorneys for the groups argue the Army has not properly investigated alternatives to open detonation.

Army Identified Instability in March

In March of this year, the Army discovered that 68 drums of lead azide stored in bunkers at the Iowa Army Ammunition Plant had begun “recrystallization,” CBS News reported. The plant, built in 1941, produces medium- and large-caliber munitions.

The crystallization process makes the material more sensitive to shock, friction, and temperature changes. Officials said they have been meticulously planning for the disposal event since that discovery.

EPA Suggests Army May Not Need Permit

In a court filing Friday, the Environmental Protection Agency suggested the U.S. The EPA response noted the court order applies only to the permit itself.

Iowans share concerns about lead azide as court ruling pauses detonation
Photo: ksbw.com

The agency cited federal regulations authorizing the Army to implement waste treatment without a permit when it determines an immediate threat to public safety exists. The Army is not a party to the environmental groups’ petition for review.

Weather Risks and Public Safety Concerns

It says the lead azide has degraded and that crystals in the waste could fracture as temperatures drop.

Federal appeals court blocks the Army’s plan to detonate 9,500 pounds of lead azide in Iowa — WCCO – CBS Minnesota

“A controlled detonation allows the Army to implement measures to minimize the risk to the public, including the risk from the ejection of partial unexploded ordnances that can explode later from the Facility,” the court filing says.

Environmental groups and local officials have challenged the safety of the operation. On Friday evening, Governor Kim Reynolds activated the State Emergency Operations Center in order for state agencies to better coordinate ahead of the planned detonation, according to KCRG.

Environmental groups challenge planned detonation at Iowa Army ammunition plant — Iowa's News Now

“Our federal government needs to do better at communicating the potential health risks of lead contamination in our communities and providing more time to keep our communities and vulnerable groups safe, like children and pregnant women,” said Sarah Green, the Executive Director at the Iowa Environmental Council.

On Friday, the St. Louis–based 8th U.S. Circuit Court of Appeals issued an emergency order halting the Army’s planned detonation of lead azide at the Iowa Army Ammunition Plant, exercising its appellate jurisdiction over the Southern District of Iowa where the case originated. The court’s intervention paused the demolition pending review of environmental groups’ challenges to the risk assessment and permitting process.

“Iowans deserve to see an Environmental and Health Impact Statement and investigation into better alternatives than this extreme planned explosion. We’re hoping the Judge halts this action before it takes place tomorrow,” said Wally Taylor, Attorney and Legal Chair for the Sierra Club Iowa Chapter.

Federal court indefinitely pauses military's plans for detonation of unstable explosives in Iowa — CBS Evening News