UW Residence Hall Wins ENR Best Higher Education/Research, Safety Awards

The University of Wyoming has completed its first new residence hall in more than 60 years, a 306,882-square-foot complex that is the largest capital project in the institution’s history, ENR reported.

The project, submitted by JE Dunn Construction, earned ENR’s Best Project award for Higher Education/Research and an Award of Merit for Safety. It replaces outdated 1960s-era housing with two towers — the six-story North Hall and five-story South Hall — delivering more than 950 beds and a two-story dining facility designed to serve the entire campus.

More than 170,000 square feet of sandstone facade anchors the buildings to the university’s Collegiate Gothic idiom, but sourcing the stone dictated the schedule before groundbreaking. The masonry package went to bid more than a year early because the sandstone meeting campus standards came from a small quarry in Utah with no guarantee it could produce enough material on a normal timeline.

“The masonry package on this project went out to bid more than a year before groundbreaking because the sandstone that could meet University of Wyoming campus design standards came from a small quarry in Utah and there was no guarantee it could produce enough stone on a normal schedule,” the project team said in its submission to ENR.

UW Residence Hall Wins ENR Best Higher Education/Research, Safety Awards

University rules mandated local trade involvement in a market lacking firms scaled for this scope. The solution paired experienced national trade partners with local subcontractors.

The North Hall functions as two buildings in one. Separate structural systems for the dining facility and the residential towers intersect at the fourth floor, forcing concrete podium slabs, structural steel, and prefabricated cold-formed metal framing with different tolerances to reconcile through enhanced layout control and tight sequencing.

Material shortages and drywall setbacks on the North Hall shaped the approach for the South Hall, which completed five months ahead of schedule thanks to strategic resequencing, selective overtime, and improved trade flow.

Steep 12/12 pitched roofs, high winds, and complex dining-hall installations drove the team toward offsite prefabrication wherever it could reduce exposure. The standout was a prefabricated cornice and roof blocking system that eliminated extensive onsite cutting and pulled workers back from steep roof edges. The cornice system more than doubled productivity while reducing onsite labor.

The site served as a classroom. University construction management students received faculty-coordinated access and internships on the job; one became a full-time employee and finished the project with the team.

Key partners included owner University of Wyoming, lead design firm alm2s, architects Mackey Mitchell Architects and Plan 1 Architects, structural engineer Martin/Martin Consulting Engineers, mechanical/plumbing/IT/AV/fire/security firm BCER Engineering, electrical engineer Cator Ruma & Associates, and landscape architect RVI Planning. Major subcontractors were Coloscapes Concrete, Encore Electric, Floorz, Great Lakes, Heartland, BD Millwork, Maximum, Puma, Pye-Barker, and RK Mechanical.