William Henry Middle Demolition Starts Dec. 7, Pending State Funding

Demolition of the closed William Henry Middle School on Carver Road begins Dec. 7, the Capital School District board announced Wednesday.

The Delaware Department of Education approved a $52.6 million certificate of necessity on Nov. 19 to demolish the building and rebuild the campus for an expanded Kent County Community School and the Kent County Secondary Intensive Learning Center, Bay to Bay News reported. The disbursement still requires approval through the state budget process next year. If fully state-funded, the district would avoid a referendum for taxpayer support.

The school has been shuttered since a tornado heavily damaged it in 2020. This was the third application the district submitted for the project; the department had approved no districts’ certificates of necessity in the previous two fiscal years.

Construction is expected to start in spring 2027 and take about 24 months. Contractor Richard Y. Johnson & Son estimates the teardown will last two-and-a-half months. A transportation depot for roughly 76 buses is also planned for the campus, with completion targeted for mid-2028.

Builders and the Department of Natural Resources and Environmental Control will enforce dust and runoff controls, including wetting the ground and structure to limit airborne debris. The section facing Kent County Community School will remain standing until winter break to act as a noise and physical barrier for the 80 students there.

“The students at KCCS — the noise would just put them in overload. I have a grandson that (that) would have happened with him,” said Vickie Pendelton, a School Board member.

“Any work done during the day, that’s going to be loud. I can see my grandson trying to get out of that building.”

Several pallets of bricks from the original William Henry Comprehensive High School — the third African American high school in the state, beginning in 1952 — will be available near the end of demolition for alumni who want them.