West Virginia regulators last week approved a $2.7 billion plan by FirstEnergy subsidiaries to build a 1.2-gigawatt natural gas plant and 70 megawatts of solar power.
- The surcharge adds $1.18 monthly to residential bills initially, rising as construction progresses.
- An unnamed data center drives the need, requesting 100 MW in 2028 growing to 1,012 MW by 2033.
- Consumer advocates and the United Mine Workers oppose the plan, citing risk to ratepayers and coal jobs.
Commission approves surcharge mechanism
The West Virginia Public Service Commission authorized Monongahela Power and Potomac Edison to recover construction and financing costs through a monthly surcharge calculated every six months until the gas plant enters base rates, expected in late 2031. The surcharge will increase residential bills by $1.18 a month, or 0.9%, initially, Utility Dive reported.
The approved gas-fired facility, called the Maidsville Energy Center, is expected to cost $2.48 billion. The commission approved the surcharge mechanism despite precedent: Pepco Holdings recovered more than $80 million from ratepayers for the canceled Mid Atlantic Power Pathway project, Utility Dive reported.
Data center demand drives capacity shortfall
The project was prompted by an unnamed data center customer requiring 100 megawatts in 2028, increasing to 1,012 megawatts by 2033, according to commission staff. Mon Power projected a 60 MW capacity shortfall in 2028 growing to 2,194 MW in 2034 with new large loads, amid surging capacity prices in the PJM Interconnection, Utility Dive reported.
Opposition centers on risk shifting and coal displacement
Consumer advocates and environmental groups challenged the project, pointing to doubts about load growth forecasts and the transfer of project risk onto ratepayers. The Sierra Club argued the utility’s $4 billion rate base would increase by 67% and urged large load tariffs to ensure recovery from the customers prompting the upgrades.
“The underdevelopment of the Companies’ CC proposal introduces significant risk of cost increases and schedule delays,” Anna Sommer, principal at Energy Futures Group, testified on behalf of West Virginia Citizen Action Group, Solar United Neighbors and Energy Efficient West Virginia, Utility Dive reported.
Brian Sanson, international president of the United Mine Workers of America, charged state regulators and political leaders with favoring natural gas companies and data center developers over West Virginia workers and utility customers. “The fix was in from day one, and West Virginia ratepayers and coal miners are the ones getting their pockets picked,” Sanson said.
Sanson disputed assurances the gas plant would operate alongside the existing coal-fired Fort Martin Power Station, arguing the new capacity will ultimately displace coal-fired production.
Caity Coyne, coalition manager for West Virginians for Energy Freedom, said families and small businesses should not finance a plant for potential data center demand without enforceable guarantees those companies will cover costs. “If trillion-dollar technology companies want to build data centers in West Virginia, they should be responsible for the infrastructure needed to power them,” Coyne said.
Commission orders future large-load negotiations
The commission directed the utilities to negotiate agreements with future large-load customers that include financial protections for existing ratepayers, but did not prescribe specific contractual terms, leaving details for future negotiations and regulatory review, wvnews.com reported.
In the “unlikely event that construction ceases or experiences extraordinary delays,” the commission will “initiate an appropriate proceeding to determine the applicable accounting and ratemaking treatment, surcharge or base rate recovery and the timing of such recovery,” the order says.