Casa Grande’s Planning and Zoning Commission tabled a rezoning request for the long-stalled PhoenixMart site on Nov. 12, delaying a mixed-use technology park anchored by a data center, Axios Phoenix reported.
The commission expects to reconsider the plan in January. Property owner AZ Sourcing LLC proposes the Casa Grande Tech Center on the 585-acre property, with a data center occupying about 6% of the site, Jon Gillespie of Rose Law Group told Phoenix Business Journal.
DataX Energy plans a “bring your own power” approach, working with the local electric district to develop clean energy sources through solar, batteries and fuel cells, Court Rich of Rose Law Group told Axios. Rich told the commission the data center would not use water-based cooling.
“The PhoenixMart site is a problem we’re all trying to solve,” Rich told the commission. “There are few users who could take over a site like this, and a data center is among the small world of possibilities,” he said.
Plans to transform the long-dormant PhoenixMart building into a data center have been delayed until January after the Casa Grande Planning and Zoning Commission voted 4-3 Thursday night to table a proposed zoning amendment following public concerns …https://t.co/AA726h5iJa
A dozen speakers, including Casa Grande residents, urged rejection of the rezoning, citing concerns about energy usage, noise, water and heat. Commissioner Chris Hubbard said that Casa Grande has a separate area designated for industrial use and she opposes a data center at the PhoenixMart site because she considers the regulation insufficient.
Commission chair Brett Benedict acknowledged he hears the concerns about data centers, but said that is not what is being voted on yet. Rich emphasized the proposed data center would require separate approval if the city OKed the rezoning request, as would any battery energy storage system.
AZ Sourcing LLC, the Scottsdale-based development company organized in 2009 that owns the 585-acre PhoenixMart property, proposes the Casa Grande Tech Center as a mixed-use technology park anchored by a data center on roughly 6% of the site. The firm applies an infrastructure-first philosophy, prioritizing early coordination with utilities and public agencies to secure power, water, and infrastructure for large, contiguous sites with long-term optionality.
Gillespie said the project’s first phase is expected to create nearly 6,800 construction jobs, which would likely draw people from the Phoenix area. The site was announced in 2012 for a 1.5 million-square-foot international trade center, broke ground the following year, and was canceled in 2019, per AZBEX.