Portland, PSU Delay Council Vote on Funding New Performing Arts Center

“Delaying a decision will not make money magically appear for this costly, risky idea,” said Karen Whitman of the Save the Keller coalition.

The City of Portland and Portland State University announced Tuesday they will not ask the City Council to vote on funding a new performing arts center in early December as widely expected.

A timeline for future council decisions will be developed through that process, the statement said.

The proposal calls for building a new 3,000-seat center as part of a PSU Performing Arts + Culture Center at 310 Market St., then remodeling the existing Keller Auditorium into an 1,800-seat theater. The previous five-member council approved the “two venues” plan subject to identifying financing.

Council Vice President Olivia Clark said in September she was “very concerned about the money” and that “there is no money.” Total city and PSU costs are estimated around $850 million, with the new center alone projected at roughly $450 million.

PSU has raised $157.6 million for its share, including $137.5 million in state bonds approved by the 2025 Oregon Legislature, $7.6 million in Portland urban renewal funds, and $12.5 million in philanthropic pledges.

A 2020 seismic analysis by Miller Consulting Engineers found the 105-year-old Keller Auditorium would likely collapse in an earthquake. A full renovation would require closing the venue for at least two years, cutting off Broadway revenue that supports the other Portland’5 venues.

Whitman said the city should instead approve a $20 million renovation of the Keller and keep Broadway shows downtown. No new date has been set for a council hearing on the proposal.