Crews Raise First Walls for New $45M Horace Mann Elementary in Fargo

Construction crews began placing precast concrete walls Monday for the new Horace Mann Elementary School in north Fargo, the first visible sign of construction for the $45 million replacement for the district's oldest building.

The milestone, reported by Valley News Live and detailed by The Forum, shifts the project from months of underground work — soil improvements, footings and foundation — to vertical assembly at 1025 Third St. N. “We call it ‘going vertical’ on the building, and it’s starting to take shape,” Walker Busse, project manager for general contractor Kraus-Anderson, told The Forum while standing on the sidewalk outside the fenced site.

The new K–5 school will consolidate students from the Horace Mann, Roosevelt and Madison attendance boundaries. Since demolition of the 1915 structure began in late June, those children have been split between Madison for kindergarten through second grade and Roosevelt for grades three through five, a temporary arrangement expected to last until the new building opens in fall 2028.

111726.N.FF.HoraceMann.2
Photo: inforum.com

“These first ones will go fairly quickly, but the larger panels will take a little bit more time for each piece,” Busse said of the precast panels, which are poured in-house at Taracon Precast in rural Hawley, Minnesota, and hauled to Fargo on semis.

Wysan Precast Services, based in Moorhead and Hawley, is using a large crane to set 8 to 12 panels a day, totaling up to 140 panels. The lightest panels weigh 10,000 to 15,000 pounds; the heaviest, destined for three-story sections, reach 45,000 to 52,000 pounds each.

Why the 1915 building came down

District officials previously cited the century-old school’s advanced age, the difficulty of making safety upgrades, a lack of lunch-serving space and the absence of collaborative learning areas as reasons to replace rather than renovate. The project is financed through a bond issuance from the district’s building fund.

Precast walls positioned by Christmas 2026

Crews expect to have all precast walls in position around Christmas 2026. Structural steel, roofing and interior work will follow. The building is scheduled for completion and turnover to Fargo Public Schools by the end of 2027 or early 2028, with furnishing and supply installation ahead of the fall 2028 opening.

Crane lifting a pale grey precast concrete wall panel over an open excavated construction site on the Great Plains
Photo: wisevoter.com

Season trajectory for aging schools

Districts across the region with buildings constructed before 1950 are increasingly weighing demolition against renovation. Horace Mann follows that pattern: officials concluded that modernizing the 1915 structure would cost more than rebuilding, a calculation playing out in similar communities facing aging infrastructure, deferred maintenance and modern code requirements.

“We call it ‘going vertical’ on the building, and it’s starting to take shape,” said Walker Busse, project manager for Kraus-Anderson.

Monday, Nov. 16, 2026: First precast panels placed. Around Christmas 2026: Precast walls fully positioned. End of 2027 or early 2028: Building turnover to district. Fall 2028: Students welcomed.