DNREC Adopts Final Cleanup Plan for Amtrak Wilmington West Yard Operable Units 1 and 3

DNREC adopted the Final Plan of Remedial Action for Amtrak Wilmington West Yard Operable Units 1 and 3 after zero public comments.

Railyard Remediation Steps

The Department of Natural Resources and Environmental Control adopted the cleanup strategy after issuing a public notice on October 7, 2026.

Operable Unit 1 covers the Amtrak Training Center, its parking lot, entrance road, and an adjacent wooded area. Operable Unit 3 contains the electrical substation and surrounding upland territory.

Key actions mandated by the final plan include the disposal of PCB-contaminated soils, with restoration including excavation, loading and offsite transportation. Crews will also implement a Contaminated Materials Management Plan and a Long-Term Stewardship Plan, record an Environmental Covenant, and submit a Remedial Action Completion Report.

Decades of Rail Operations

Amtrak acquired the property in April 1976 from the Pennsylvania Central Transportation Company under the Regional Rail Reorganization Act of 1973. The facility was formerly electrified with overhead catenary wires that were later removed, though the structures remain.

State oversight began decades ago when the DNREC underground storage tank branch investigated soil impacts near three abandoned oil tanks in 1992, overseeing the abandonment of three oil underground storage tanks within the electrical substation enclosure that had been abandoned in place and were reported to contain mineral oil.

Subsequent assessments in 2001, 2017, and 2018 confirmed that organic compounds and heavy metals exceeded standard screening benchmarks. In November 2013, Amtrak entered the site into the Voluntary Cleanup Plan Program with DNREC, and later prepared a Remedial Investigation Workplan in May 2017, completed the Remedial Investigation in 2019, and had the Remedial Investigation report approved by DNREC in August 2022.

Proposed remedial action operable unit l

Amtrak and Norfolk Southern Share 38-Acre Property

Amtrak oversees the 38-acre property, while Norfolk Southern Corporation leases a portion of the tracks. The facility borders mainline tracks on its western edge, Beech Street to the north, an Interstate 95 drainage ditch to the east, and Little Mill Creek toward the south.

Workers built the High-Speed Training Center on the northern section of the grounds between 1999 and 2000. Besides minor repairs, the location has functioned primarily for staging railcars, equipment, and materials since 1884.

State oversight of the rail facility connects to the broader mandate of the Department of Natural Resources and Environmental Control, an executive-branch cabinet agency established in 1970 by the Delaware General Assembly. Within the agency, the Division of Waste and Hazardous Substances holds the specific purview to investigate and clean up contaminated sites and ensure adherence to environmental laws.

Contact Information

For additional information, please contact Gina Marinacci, Project Manager, DNREC Division of Waste and Hazardous Substances, Remediation Section, 391 Lukens Drive, New Castle, DE 19720, by email at [email protected], or by phone at 302-395-2600, according to DNREC.