The Wyoming Intertie project alone would more than double the 1,320 megawatts now moving between the eastern and western grids, the Mountain West News Bureau reported.
- DOE intends a $2.8 billion loan to Grid United for a $4 billion, 1,800-megawatt Wyoming Intertie.
- Construction is set to begin in 2030 with completion within three years.
- Grid Strategies research shows initial costs may fall on ratepayers before long-term savings cancel them out.
- Xcel Energy also won federal support to expand a Colorado–Texas link from 210 to 700 megawatts.
The U.S. Department of Energy recently announced it intends to loan Grid United $2.8 billion, covering most of the estimated $4 billion cost, to build more than 100 miles of transmission lines across Carbon and Albany counties to a hub in Platte County near the Nebraska border. The Wyoming Intertie is designed to move 1,800 megawatts in either direction by 2033, according to the Mountain West News Bureau.
“They were built to move relatively small amounts of power across the seams between the grids,” said Jay Caspary, principal at TransGrid Advisors and a power systems engineer.
There are seven existing facilities that currently connect the two grids along a seam running east of the Rockies from Miles City, Montana, to eastern New Mexico.
Greg Beard, who runs the DOE’s Office of Energy Dominance Financing, said on a press call the project will create hundreds of short-term construction jobs and long-term operations positions while giving Wyoming producers “another way to sell power into fast-growing regional markets.”
A Grid Strategies study cited by the bureau shows household ratepayers could bear the upfront costs of stitching the grids together, but the greater long-term savings eventually cancel that out. “The bigger you make the grid, the more levelized the prices are for everybody,” Caspary said.
DC ties also let operators shift generation from areas untouched by extreme weather into storm-hit regions.
“If you go a few hundred miles away, the storm’s not there and the weather’s much milder. Gas generation’s available. It just can’t get to the market. These DC ties allow you to move resources from one area that may not be affected by the storm to another one,” Caspary said.
Grid United is also developing a 3,000-megawatt Montana–North Dakota link, an 1,800-megawatt Pueblo–Oklahoma panhandle line, and a 1,500-megawatt southeast New Mexico–El Paso connection, all with federal support. Xcel Energy separately secured federal funding to expand a Colorado–Texas link from 210 to 700 megawatts, with room to reach 2,000 megawatts as demand grows.
The US Department of Energy said on Tuesday it is offering a conditional loan commitment of up to $2.8 billion to the Wyoming Intertie power transmission project that aims to lower power costs and strengthen grid reliability in the US West. https://t.co/82uj5Rv0Ht