The Interstate Bridge Replacement Program received a single design bid in late September from a joint venture led by Kiewit Engineering Group, a contractor whose current Oregon project is running more than two years behind schedule and triple its original budget.
That bid — the only one submitted for a contract estimated at $3.9 billion — arrived months after Maryland dropped Kiewit from the Francis Scott Key Bridge rebuild, calling its price and timeline “unreasonably high and therefore unacceptable,” according to a statement from Gov. Wes Moore’s office.
The same firm has drawn negative marks on four consecutive annual performance reviews from the Oregon Department of Transportation dating back to 2022, the Portland Daily Journal of Commerce reported.
“Having multiple bidders is important to protect the taxpayers. If you only have one bidder, they can bid whatever they want.”
Rep. Ed Orcutt, R-Kalama, co-chair of the Joint Oregon-Washington Legislative Action Committee
The joint venture, named Columbia River Constructors, includes Guy F. Atkinson Construction and Traylor Bros. Inc. alongside Kiewit. The contract they are positioned to win covers two replacement bridges, their approaches, connections at Hayden Island and State Route 14, and demolition of the existing spans.
Cost trajectory doubles in two years
The overall program price tag has nearly doubled since 2022, when officials estimated a maximum of $7.5 billion. By March of this year, that figure climbed to $14.4 billion. Washington Gov. Bob Ferguson said construction contracts will be awarded next year, with traffic crossing the new span by 2035 — roughly two years later than previously announced.

A pattern of overruns in Oregon
Kiewit’s track record on the Interstate 205 Abernathy Bridge in Oregon City illustrates the concern. Originally priced at $250 million in 2018, the project now carries an $800 million estimate and remains more than two years behind schedule, KGW reported.
On the Hood River-White Salmon Bridge Replacement Project, hired in 2024, the cost has already doubled to more than $1.2 billion. Economist Joe Cortright of City Observatory attributed part of that increase to the company underestimating drilled shaft costs.
Cortright told the legislative committee on Monday that the program is in an active dispute with Kiewit, that Kiewit goes over budget, and that the program has been unable to negotiate with them.
Kiewit spokesperson Bob Kula said the company does not comment on potential project pursuits but added, “we stand behind our long track record delivering complex transportation projects across the U.S.”

Lawmakers split on single-bid risk
At a Monday meeting of the Joint Oregon-Washington Legislative Action Committee, Rep. Thủy Trần, D-Portland, and Sen. Bruce Starr, R-Dundee, pressed administrators on accountability and cost management. Yet other legislators expressed comfort with the arrangement. Rep. Susan McLain, D-Forest Grove, said the three firms bring a wider range of resources and expertise.
“There are very few firms in the country that have the capacity or experience needed to take on a project of this size,” she said in an email.
Rep. Jake Fey, D-Tacoma, chair of the House Transportation Committee, noted two interested firms chose to collaborate. “What are you going to do? If you can’t make a deal with them, then we go back to the process of seeking qualified bidders,” he said.
Progressive design-build as a hedge
Program officials are counting on a progressive design-build delivery method to provide cost certainty. The approach brings the owner, designer, and contractor together early in the process. “The method is known for its greater cost certainty and transparent pricing,” said John White, a Washington state transportation official, responding to cost concerns at the hearing.
The existing I-5 bridge, parts of which date to 1917, carries 138,000 vehicles daily across the Columbia River and sits in a seismic zone. A replacement has been studied for decades.