LADWP Secured $28 Million Federal Grant for Los Angeles Groundwater Project

The Los Angeles Department of Water and Power secured an additional $28 million federal grant for the Los Angeles Groundwater Replenishment Project on Monday.

The award, anticipated through the U.S. Bureau of Reclamation’s large-scale water recycling program, brings total federal support for the project to $88 million, building on $60 million previously awarded, Public Power reported. The funding targets construction at the Donald C. Tillman Water Reclamation Plant in the San Fernando Valley. LADWP said federal investment helps offset costs to minimize customer rate impacts.

$1 billion project to serve 500,000 residents

The $1 billion initiative is the largest potable reuse project under development in the United States. Once operational, it will produce up to 45 million gallons of purified recycled water per day, replenishing the San Fernando Groundwater Basin and serving approximately 500,000 Angelenos, LADWP said. The project is a joint effort between LADWP and Los Angeles Sanitation and Environment (LASAN).

Construction on the advanced water purification facility at Tillman began in December 2024. Jacobs holds the progressive design-build contract, including startup and commissioning. The utility targets completion by the end of 2027.

Wastewater treatment basins at the Donald C. Tillman Water Reclamation Plant in Van Nuys
Photo: goldencoastjournal.com

Three-step purification yields up to 20 million gallons daily

The new facility will treat water that has passed through Tillman’s existing process through three additional steps: membrane filtration, reverse osmosis, and ultraviolet advanced oxidation. The city’s May engineering report modeled treating up to 25 million gallons daily to produce up to 20 million gallons of purified water.

Two equalization tanks, each holding 4.6 million gallons, will absorb daily flow variations. Electrical upgrades at Tillman and roughly two miles of underground conduits and vaults for a new power connection are also planned.

From plant to basin

Purified water will move through an existing pipeline to the Hansen Spreading Grounds. Los Angeles County Public Works will control deliveries based on basin capacity. Most deliveries are expected during dry weather; stormwater takes priority during wet periods. The city plans to refurbish an existing outlet and add a second at another basin to maintain deliveries during maintenance or stormwater capture.

Federal funding trajectory

Reclamation first selected the project for $30 million in May 2024 for final design and construction at both the existing plant and the new purification facility. That award counts toward the $60 million previously reported. The bureau’s public listing for the 2026 competition still described applications as under review as of the November announcement.

Mayor Bass calls project vital for climate resilience

"The decisions we make today will shape Los Angeles for generations to come.”

The project recently received the Chairman Award at the Los Angeles Business Council’s 56th Annual Architectural Awards. It also lays groundwork for Pure Water Los Angeles, a future large-scale recycled water initiative, LADWP said.