The Cost of Keeping Montgomery County’s Incinerator Running
Montgomery County faces a defining choice regarding its waste management strategy, as the debate over the future of the Dickerson incinerator intensifies. While the facility is officially termed a Resource Recovery Facility (RRF), its long-term viability has come under fire. According to a guest commentary published by Maryland Matters, the path forward is not merely a question of logistics, but one of fiscal and environmental priority. The core of the issue lies in whether the county should commit hundreds of millions of dollars to upgrade a facility that may ultimately hinder its ability to meet modern recycling and waste reduction goals.
The financial stakes are significant. A staff report from September 15, 2026, highlighted that the county’s contractor estimated a $356 million requirement to bring the incinerator up to higher standards. This figure, however, is likely a floor rather than a ceiling. The county noted that a competitive procurement process could drive costs even higher. Crucially, that initial estimate excluded the logistical and financial burden of relocating ash disposal, a byproduct of the incineration process that requires specialized handling.
The Hidden Burden of Ash Disposal
If the county opts to maintain the RRF, it must secure a long-term home for its toxic ash. The report points to the Interstate 95 landfill in Fairfax County, Virginia, as a potential destination. Yet, this is far from a simple solution. The landfill would require additional capacity to accommodate Montgomery County’s waste, a move that would inevitably increase costs—costs that remain uncalculated by staff. If that option falters, the county faces the prospect of continuing to send ash to Henrico, a site that is not a dedicated monofill and is already considered an overburdened community.

Alternative sites, such as the Brunswick monofill in Maryland, present their own challenges. The staff report explicitly warns that shifting disposal to Brunswick would result in additional costs and necessitate a long-term contract. For a county attempting to pivot toward sustainability, locking into a long-term contract for incinerator ash disposal is a move that runs counter to the goal of reducing waste output.
Incentives and the Recycling Gap
The fundamental problem with the incinerator model is that it creates a structural disincentive for waste reduction. Incineration requires a steady stream of trash to remain operational and cost-effective. Because the current contract for the Dickerson incinerator is based on fixed costs, the county does not see financial relief even if it succeeds in reducing the volume of waste sent to the facility.

“Costs and solid waste charges with Advanced Waste Processing (AWP) and long-hauling of residual waste to a landfill are projected to be similar to the costs for upgrading and retaining the RRF.”
This contrast is stark. With a long-haul approach—transporting waste to landfills—the county would pay on a per-ton basis. This creates a direct financial incentive to prioritize recycling, composting, and advanced waste processing. As the staff report notes, the current cost estimate for upgrading the incinerator did not account for the potential savings available under a long-haul model, where reducing trash generation directly lowers the county’s expenses.
The Choice Between Two Imperfect Paths
Opponents of moving toward a landfill-reliant system correctly point out the ethical concerns of exporting waste to neighboring states. However, the current incinerator model does not eliminate this problem; it merely transforms the nature of the waste from standard municipal refuse to highly concentrated, toxic ash. The question, therefore, is not whether to landfill, but what kind of waste the county produces and how it manages the financial incentives for its residents.
In a tight budget environment, the decision to spend hundreds of millions on an incinerator upgrade could effectively crowd out investment in the technology and education necessary for a circular waste economy. If the county commits to the RRF, it risks trapping itself in a system that prioritizes burning over reduction for years to come. Transitioning to long-haul disposal, while not a perfect environmental solution, provides the fiscal flexibility to pursue more sustainable waste management practices as technology and infrastructure evolve.