Oregon’s new fast-track law for clean energy projects has been used by just two developers since February, even as the state ranks last nationally for permitting speed, a position that jeopardizes its 2040 carbon-free electricity goal.
House Bill 4031, passed by the Legislature in February, lets certain projects bypass the state Energy Facility Siting Council and apply directly to counties.
County officials approved both projects — the Well Springs Solar Project in Morrow County and a 69-turbine wind farm in Gilliam County — in September, completing a process measured in months rather than years. Brian Walsh, vice president of project development for MN8 Energy, said the switch to Morrow County jurisdiction shaved more than a year off the siting timeline.
“That’s a tremendous savings for the project, and also keeps the price of power lower for those who buy the power and consume the power,” Walsh said.

Permitting lag
Gamba said he plans to tighten the state’s process in the 2027 legislative session.
Limited eligibility
The Oregon Department of Energy identified seven projects eligible to switch to local jurisdictions under HB 4031. Thirteen others did not qualify and remain in the state queue.
“Now, you can argue whether they’re as thorough as they should be or not.”
Opposition to the two county-approved projects was minimal: none for the Gilliam County wind farm and only one formal objection to Well Springs.
Lively said even if only one or two projects are completed in time to capture federal tax credits, the law will have been worth it. “It would be nice to see more,” he acknowledged.
Worth a look
- DOJ Awards Nearly $150 Million to Hire Over 1,000 Officers Through COPS Hiring Program
- Idaho Paid Hunters $24,000 to Kill 12 Newborn Wolf Pups in April
- Bank of England Policymakers Say High Energy Costs Could Force December Rate Hike (newsarchyuk.com)
- Jackson State vs Delaware in Newark Saturday for Regular-Season Finale (world-today-news.com)