Ottawa Tables Motion to Expand Expropriation Powers for Alto Rail

Ottawa moved Friday to strip away the remaining standard expropriation rules for the Alto high-speed rail project, posting a 521-page notice of ways and means motion that would let the government seize land without public hearings and transfer deeds directly to a private consortium.

  • Draft Budget 2026 implementation legislation would exempt Alto from the Expropriation Act, Railway Relocation and Crossing Act, key sections of the Railway Safety Act and the Impact Assessment Act.
  • Landowners could face an eight-year right of first refusal and a four-year work prohibition before Ottawa decides whether to expropriate.
  • Defective expropriation notices would automatically seize 100 per cent of a property’s rights and wipe out existing easements, leases or rights-of-way.
  • Farm and municipal crossing disputes would go to private arbitration with costs split up to $25,000 per party plus legal fees.

From targeted exceptions to a bespoke regime

In March, Parliament enacted the High-Speed Rail Network Act via Bill C-15, permitting Alto to bypass initial purchase talks and substitute public hearings with written objections while retaining the project under the Expropriation Act. The new motion, tabled November 20 as the first step toward the Budget 2026 Implementation Act, No. 1, would scrap that remaining oversight, CBC reported.

“Both in terms of dollar value and the number of private properties required, in my view, it will be the largest expropriation project in modern Canadian history,” said municipal and land-use planning lawyer Ajay Gajaria.

Eight-year freeze, four-year work ban

The draft expands the minister’s discretion to consider “any factor … including the public interest” before registering a work ban. A prohibition on work bars owners from building, adding major extensions, digging or making significant improvements without the transport minister’s permission, and any value added during that period is excluded from the expropriation payout.

“Somebody looking to purchase your property is going to see the presence of a right of first refusal for the Crown to essentially match the best offer,” Gajaria told CBC.

Owners in the corridor “may have a circumstance where you cannot market or sell your property potentially for eight years, potentially longer.”

A November 12 landowner guide from the law firm OMH states that the existing right-of-first-refusal notice can already remain on title for up to eight years and that owners hit with a work prohibition are entitled to compensation for actual losses, The Toronto Journal reported.

Canada alto high speed rail expropriation powers
Photo: nglobenews.com

Defective notices seize everything

Since March, officials have been able to fix defective expropriation notices and backdate corrections to the original filing date. The new motion goes further: when a notice omits the exact land being taken, it automatically seizes 100 per cent of the owner’s property rights and wipes out existing easements, leases or rights-of-way.

“You likely will get compensated,” Gajaria said. “The intent is that a person who is expropriated for a public project gets full and fair compensation for the property.”

Crossings forced into paid arbitration

Because trains running up to 300 km/h require every crossing to be grade-separated — a concrete overpass or underpass — the bill would force severed landowners into private arbitration and make them split costs up to $25,000 per party on top of their own legal fees, The Toronto Journal reported. Arbitrators could also bill landowners for part of building or maintaining a crossing.

“I do think that provision goes too far,” Gajaria said.

Political split

The Conservative Party and Bloc Québécois oppose the Alto project, citing the planned expropriations. The NDP supports high-speed rail but has reservations over the sweeping powers.

“With high-speed rail, you don’t have the latitude to go around things … So sometimes expropriation is necessary, but that’s the last resort,” NDP Leader Avi Lewis said.

“Some of it’s going to be public land, some of it’s gonna be private land … but we need these projects. It’s a vast country.”

Alto declined to comment on the proposed legislation.

The government calls Alto a “bold step to address [Canada’s] growing transportation needs” and part of a national “transformative strategy” designed to begin construction years ahead of schedule. A recent Alto-commissioned study projects $24.5 billion in annual economic benefits once the line is operating.