Power Restored in Northwest Columbia After Substation Outage Affects 5,558 Customers

A power outage hit northwest Columbia just as the morning commute began Wednesday, leaving 5,558 Columbia Utilities customers in the dark and knocking out traffic signals along a major corridor.

The disruption centered on the Harmony Branch substation, where a blown fuse and a tripped breaker collided with routine maintenance on two switchgear units, Columbia Utilities spokesperson Jason West said. “The short answer is the substation woke up on the wrong side of the bed this morning and was being a drama queen when the crews were trying to restore power,” he said.

Boone County Joint Communications alerted drivers around 6:55 a.m. that a “large amount” of traffic lights on Stadium Boulevard were not working. The outage map showed the affected area stretching along Stadium Boulevard from Rollins Road up to Worley Street, with a separate outage on North Fairview Road persisting until around noon.

“Phones at two nearby middle schools worked during the outage, but computer systems connected to them did not, and power has since been restored to the schools.”

Columbia Public Schools spokesperson Michelle Baumstark said. Power was intermittent during arrival at the two middle schools, while the rest of the district starts at 8:20 a.m. Service returned around 8 a.m., she said.

The Harmony Branch substation was already undergoing routine maintenance on two switchgear units when the fuse blew and the breaker tripped, West explained in a follow-up email.

Power Restored in Northwest Columbia After Substation Outage Affects 5,558 Customers
Photo: columbiamissourian.com

Columbia Utilities crews restored power to most customers shortly after noon. The utility’s outage map, which tracks customer counts in real time, showed the peak impact at 7:40 a.m. with 5,558 customers affected.

Dark traffic signals along Stadium Boulevard created the most immediate public safety concern during the morning rush. Drivers encountering malfunctioning signals are required to treat them as four-way stops.

Baumstark confirmed that power was fully restored to schools by roughly 8 a.m., limiting the instructional disruption.

Power was fully restored shortly after noon, West confirmed.