Prologis Sues Trenton Over 250-Megawatt Data Center After Voters Approve 25-Megawatt Cap

Trenton voters approved a charter amendment banning data centers over 25 megawatts on Nov. 3, and the developer of a planned 250-megawatt campus sued the city nine days later to keep building.

The measure, known as Issue 17, passed with about 80% support, cleveland.com reported. It defines a data center as potentially including multiple buildings on a single parcel or aggregated neighboring parcels, with the 25-megawatt threshold applied to the combined monthly electrical demand or peak load of the entire development — not to each building individually.

Prologis, the developer behind Project Mila, filed suit in U.S. District Court for the Southern District of Ohio on Nov. 12, chipdispatch.com reported. The company says it holds a zoning certificate issued in December 2025 and has invested $42.3 million in the nearly 900,000-square-foot facility planned for Amazon Web Services in the city’s industrial park. The company filed the case on Thursday, naming Trenton as the defendant, the Journal-News reported.

Prologis Sues City of Trenton Over Project Mila Data Center Restrictions — WCPO 9

The charter language defines construction broadly to include infrastructure, preparations and modifications undertaken for a common purpose, cleveland.com reported. The amendment calls itself “self-executing” and does not require a separate implementing ordinance. It contains no express exemption for projects that received approvals before the vote, but it also does not state that earlier approvals are automatically invalidated or direct the city to revoke them.

Prologis argues the new restriction cannot be applied retroactively to a project the city already authorized. “The city had already approved and permitted Prologis’ data center project and the company has begun construction,” the company said in its filing, according to chipdispatch.com.

“The city’s approvals and Prologis’ investment came before the Nov. 3 vote.” By June 2026, crews had moved about 325,000 cubic yards of soil and nearly completed the underground grounding system and cable trenching, the outlet reported.

trenton
Photo: wcpo.com

Residents who backed Issue 17 formally demanded on Nov. 9 that the city revoke the zoning certificate. “When 80% of Trenton voters overwhelmingly say they don’t want data centers over 25 megawatts, Prologis should respect the will of the people,” said Nick Owens, an attorney with Conserve Ohio representing residents, wcpo.com reported.

Larie Blankenship, a member of the ballot campaign, told the same outlet: “A lot of people are still gonna be affected by this facility. It has a contiguous border with farmland that’s being farmed. There’s still a lot of damage that’s gonna be caused by this facility.”

The city responded that it is waiting for the Butler County Board of Elections to certify the results and that the matter is now before the courts.

“The application of Issue 17 to the Prologis development is now before the federal court. The City will defend the action and protect the interests of the city,” a city representative said in a statement to wcpo.com. The city of Trenton released a statement saying the issue is “now before the courts for determination” rather than for City Council to resolve, spectrumnews1.com reported.

Construction trucks continue to enter the industrial park while the case proceeds, spectrumnews1.com reported. Owens said residents are evaluating further legal options, including intervening in the federal case and pursuing a mandamus action in state court. “And we do intend to pursue all legal options, including in federal and state,” Owens said, spectrumnews1.com reported.