Richmond Schedules Coliseum Demolition by December 2027, Council to Weigh $15M State Fund

The administration will seek City Council approval in December to accept $15 million from the Commonwealth for a dedicated Coliseum Demolition Fund.

Demolition of the Richmond Coliseum is now scheduled for completion by December 2027.

  • Pre-demolition planning by Timmons Group runs through the second quarter of 2027.
  • City Council will consider legislation in December to accept $15 million in state funding for a dedicated demolition fund.
  • The Greater Richmond Convention Center Authority plans to contribute additional financial resources.
  • The roughly 10-acre site is targeted for a GRTC transit hub, housing and retail.

Avula announces revised timeline

Mayor Danny Avula disclosed the updated schedule in a press release Tuesday, Nov. 24, saying the city is making “meaningful progress towards the redevelopment of the Coliseum site and broader City Center area, including the long-awaited demolition of the Richmond Coliseum,” WRIC reported.

Timmons Group is conducting pre-demolition planning and design work expected to conclude in the second quarter of 2027, with demolition and site work finished by December 2027, according to the city’s official statement.

Administration to propose accepting state funds for demolition

In December, the administration will introduce legislation for Richmond City Council to formally accept $15 million from the Commonwealth of Virginia and establish a dedicated Richmond Coliseum Demolition Fund, Avula said.

The fund is intended to “ensure that the state’s investment in our downtown redevelopment is used in a timely and accountable manner,” the mayor’s office stated. The Greater Richmond Convention Center Authority plans to commit financial resources beyond the state allocation and continue its partnership on the project, Virginia Business reported.

Photo: richmond.com

A decade of false starts

The coliseum has sat closed since 2019, leaving about 10 acres near VCU Health, the Virginia State Capitol and the convention center underused. Under former Levar Stoney, the city issued a request for proposals in 2017 that included a replacement arena. Stoney later backed the $235 million Navy Hill project with a 17,500-seat arena, but Richmond City Council voted it down in February 2020.

A 2023 effort by the Economic Development Authority and GRCCA sought proposals without a new arena, but those plans stalled without a Council decision. Avula inherited the unresolved site upon taking office in January 2025 and said in March he hoped demolition would occur by year’s end.

Transit hub planned nearby

The city is also planning a permanent GRTC bus transfer hub at 500 N. 10th St. that could include residential and commercial uses in two towers. Officials previously said they expected to select a developer for the project, though the project’s status was not clear Tuesday and Avula and the Richmond Economic Development Authority did not immediately respond to requests for comment, Virginia Business noted.

“These are important steps to finally move this project forward, and I’m truly grateful for the partnership with the Commonwealth, the City’s Economic Development Authority, and GRCCA and Timmons for helping to make this possible,” Avula said.