The North Carolina State Ports Authority accepted a proposal from Silvi Materials on November 16 to build a deep-water cement import terminal at the Port of Wilmington.
The 30-year lease covers roughly 3.88 acres and includes two options to extend for an additional decade each. Plans call for a 100,000-ton storage dome, a pneumatic ship unloader, two rail loadouts and four truck loadouts, with construction slated to begin in spring 2028 and commercial operations targeted for autumn 2029.
“Our continued investment in North Carolina reflects our confidence in the region and our commitment to building a supply network that can support our customers for decades to come,”
The Wilmington facility will sit alongside a separate Silvi project at the Port of Morehead City, where two 100,000-ton domes and a direct Norfolk Southern rail connection are expected to come online in late 2027.
Together the two sites would provide 300,000 tons of storage capacity and access to both of the Southeast’s major rail networks — CSX at Wilmington and Norfolk Southern at Morehead City — a configuration described as a coordinated regional infrastructure network rather than an isolated port bet.

Silvi, a privately held supplier founded in 1947 and based in Fairless Hills, Pennsylvania, has been quietly assembling a North Carolina footprint. The company acquired Eagle Rock Concrete in 2025, adding nine ready-mix plants in the Raleigh-Durham market, and opened a Southeast regional headquarters in Raleigh on November 1, 2026. The port terminals extend that downstream presence upstream into import logistics.
“Silvi Materials has been a tremendous partner to North Carolina and our state ports,” said Brian Clark, Executive Director of North Carolina Ports, in the same release. “This project will enhance the region’s access to essential construction materials, helping support continued growth and development across North Carolina.”
The authority and the company did not disclose the lease rate, the capital budget for the dome and unloading system, or the volume of cement they expect to move annually.
Storage capacity is not throughput; a 100,000-ton dome can turn multiple times a year or sit half-empty depending on shipping schedules, rail velocity and local demand. Commercial returns will hinge on terminal investment costs, cement import economics, inland transportation efficiency and sustained customer demand — variables the press materials do not quantify.
The Port of Wilmington’s 2031 Strategic Plan identifies integrated bulk handling as a priority, but the document does not spell out how this specific lease advances those targets beyond adding a new tenant. Silvi’s existing import operation in Bristol, Pennsylvania, offers a template, yet the Pennsylvania facility serves a different hinterland with different rail economics.
Permitting, final engineering and financing must be completed before the spring 2028 groundbreaking. The Morehead City terminal, already under development, is scheduled to start operations in late 2027 — the first real test of whether the dual-port model delivers the distribution flexibility Silvi and the ports authority are counting on.