TCEQ Resumes Data Center Permits After Abbott Pause; Successor Hinojosa Wanted Freeze Kept

“Texans are tired of this political theatre.”

Sam Law, a researcher at FracTracker Alliance, delivered that verdict Tuesday as the state’s environmental agency quietly lifted a two-month freeze on data center permits — a freeze the outgoing governor ordered but his successor vowed to keep.

The Texas Commission on Environmental Quality resumed its normal review of air and stormwater permits for data center projects on Friday, The Texas Tribune reported. The agency said it received notice from Gov. Greg Abbott’s office that the Electric Reliability Council of Texas had finished gathering information on community impacts, one of several study topics Abbott assigned in August.

Abbott paused environmental permitting on Sept. 21, writing that TCEQ should wait until ERCOT “completes its review.” He also halted grid interconnection approvals while the grid operator audited 465 projects seeking connection, scrutinizing tax incentives, power use, water use and neighborhood effects.

ERCOT told the Public Utility Commission on Nov. 5 that it had responses from 93% of those projects, enough for “a statistically meaningful analysis.” The full report is due to the PUC on Dec. 10, with discussion set for the commission’s open meeting Dec. 17.

TCEQ Resumes Data Center Permits After Abbott Pause; Successor Hinojosa Wanted Freeze Kept
Photo: ksat.com

Then came the election. On Nov. 3, Abbott lost his reelection bid to Democrat Gina Hinojosa, who campaigned on keeping the permit pause in place until the Legislature writes new guardrails. Neither Abbott’s office nor Hinojosa’s media team on Tuesday immediately responded to a request for comment.

“The TCEQ is asserting that ERCOT has concluded its assessment of the community impacts of data centers, and without sharing those results with communities or detailing how the TCEQ will incorporate the findings into permitting decisions, agency leadership has begun unilaterally issuing data center permits.”

Kathryn Guerra, TCEQ watchdog campaign director for Public Citizen

Public Citizen called on the three TCEQ commissioners to resign, arguing the agency is rubber-stamping projects before the public sees ERCOT’s findings. FracTracker’s Law echoed the demand for a “true moratorium” and accused state leaders of theatrical governance.

Opposition to the facilities has crossed party lines in communities across Texas this year. Residents and local officials — Democrats and Republicans alike — have warned that the massive electricity demand could destabilize a grid still scarred by the 2021 freeze, drive construction of new gas-fired power plants, and drain water supplies in a state gripped by drought. TCEQ’s permits cover air emissions from on-site generators and stormwater runoff during construction.

The agency’s compliance with Abbott’s order was already shaky. In October, Public Citizen and FracTracker Alliance noticed that some data center construction permits were still being cleared. TCEQ said it suspended those permits, then took the unusual step of shutting down its automated electronic filing system and requiring paper applications for staff review.

Abbott’s August directive to ERCOT and the PUC remains posted on the governor’s website, as does his September letter to TCEQ. Both frame the reviews as a response to explosive growth in load requests from hyperscale operators.

What happens next hinges on two dates: Dec. 10, when ERCOT delivers its final report, and the 2027 legislative session, where Hinojosa has promised to codify a pause into law. Until then, the permits move forward.