White Sands Missile Range broke ground on Nov. 10 on a $27 million microgrid designed to keep its northern test facilities running for two weeks without outside power, the U.S. Army Corps of Engineers Albuquerque District reported.
The Stallion Range Power Generation and Microgrid project will serve four facilities at Stallion Base Camp with a 600-kilowatt solar array, propane generators and a 500-kilowatt battery storage system, according to the Corps. Fourteen days of energy and potable water autonomy is the design target.
“This $27 million military construction project is part of the Energy Resilience and Conservation Investment Program and was awarded this August in direct execution of the Army Directive on U.S. Army Installation Energy and Water Resilience Policy,” said Lt. Col. Brian Williams, commander of the Albuquerque District, at the groundbreaking ceremony.
Col. Michael Lueckeman, the White Sands Missile Range garrison commander, tied the project directly to the range’s core mission. “This investment ensures that critical test data is collected, test schedules remain intact, and operational readiness is maintained,” he said.
The Albuquerque District will oversee construction and field administration on a 17-month timeline. The Louisville District acted as the contracting authority, while the Corps’ Huntsville Center provided technical design support — a “team of teams” delivery model the district has used before.

In 2025 the same partners completed a $10.6 million design-bid-build microgrid for four potable-water wells on the range, the Corps said. That project set the template for the current, larger installation at Stallion Base Camp.
A microgrid operates either connected to the commercial grid or independently, isolating its load when the wider system fails. The Stallion project adds water resilience to that electrical islanding capability, a combination the Army’s installation policy now requires for critical test infrastructure.
Construction is scheduled to finish in spring 2028.