Wisconsin Regulators: Peak Power Demand to Jump 40% by 2032, Data Centers Drive 70% of Growth

Wisconsin regulators on Thursday approved a state energy assessment showing peak electricity demand will jump more than 40 percent by 2032, with three data center projects driving 70 percent of that growth, WPR reported.

The Public Service Commission of Wisconsin finalized its strategic energy assessment for 2026 through 2032, identifying hyperscale campuses in Mount Pleasant, Port Washington and Beaver Dam as the primary force behind the surge. Summer Strand, the commission’s chair, called the projected increase unprecedented after years of relatively flat demand.

“Prior to the data center, or hyperscaler, situation taking off in Wisconsin, there was electrification and some energy transition things happening, and that was maybe creating a little more demand,” Strand told WPR. “But nothing like 40 percent — 40 percent is a massive number.”

Strand also warned that the commission lacks adequate legal tools to plan for the spike while protecting ratepayers and the environment. Wisconsin has a goal of 100 percent carbon-free electricity by 2050, but no statutory mechanism requires utilities to meet it.

Generation mix leans on gas and solar

Utilities plan to add 14.4 gigawatts of generation to meet the rising load. Solar accounts for 5.8 GW and natural gas for 5.2 GW, with wind and battery storage making up the remainder, according to the PSC report cited by WPR.

Utilities say new gas plants are needed because the North American Electric Reliability Corporation has warned of an “elevated risk” of electricity shortages in the Midwest beginning in 2028.

Madison: Report shows 3 Wisconsin data centers account for 70 percent of growth in peak electricity demand
Photo: wisconsin-express.com

Environmental groups say gas build-out threatens climate goals

A Sierra Club report argues that a national rush to build gas plants could erase 15 years of emissions reductions from coal retirements. By 2030, the U.S. power sector could emit more carbon dioxide than it has since 2011.

Cassie Steiner, campaign coordinator for the Sierra Club’s Wisconsin chapter, said those trends are “echoed in Wisconsin.”

“Even if the data centers pay for the infrastructure and the fuel, we all will be paying for this in the severe climate impacts and the health impacts that are going to come from all of this new fossil fuel generation,” Steiner told WPR.

Utilities pursue ‘all of the above’ strategy

We Energies, the state’s largest utility, plans nearly 4.6 GW of new gas capacity and 4.1 GW of solar. Both the Port Washington and Mount Pleasant data center campuses sit in its territory. The utility’s parent company, Wisconsin Electric Company, declined to provide projected 2032 carbon emissions in its regulatory filing, saying the information was not available.

“Our ‘all of the above’ plan includes major investments in solar, wind and battery storage, supported by state-of-the-art natural gas generation that can operate when the sun is not shining or the wind is not blowing,” spokesperson Brendan Conway said in a statement.

Alliant Energy, which will serve the Beaver Dam project, plans 356 megawatts of upgraded gas capacity at three existing sites and 790 MW of renewables by 2032. The company projects its 2032 emissions will be 49 percent below 2009 levels and reaffirmed a net-zero-by-2050 target.

Anna Haensch, an associate research professor at UW–Madison’s Data Science Institute, told WPR that utilities pivoted back to fossil fuels as demand projections surged.

“The reason we are getting so much natural gas right now is because we need what’s called ‘firm power,’” she said. “Data centers need power that’s going to show up 24/7, around the clock, super reliable in rain, sleet or snow. And that’s fossil fuels.”

Haensch added that Wisconsin is on track to nearly double wind and solar capacity by 2032, but utilities are not retiring old fossil plants and are adding new ones.

“It’s not enough to just stop making a mess in your room,” she said. “You have to clean it up as well.”

PSC chair presses Legislature for stronger planning authority

Strand said the commission’s primary planning tool — the strategic energy assessment — “has no teeth.”

“We’re not really opining or editorializing, and we’re definitely not saying yea or nay on a comprehensive plan,” she told WPR. “We’re gathering data and information, analyzing that and then publishing information.”

She called for integrated resource planning, a process used in other states that gives regulators authority to review and approve utilities’ long-term generation plans.

Strand said such authority would let the commission address pressure on energy bills and climate concerns in a coordinated way.

“If ever there was going to be a time to help kind of restore the commission’s proper oversight role in generation and resource planning, now is the time,” she said.