Logging trucks have thundered past Amber and Andrew Ngundue’s home on 145th Street for two years, hauling timber from the bottomland forest behind their house in southeast Pulaski County, Arkansas Times reported.
AVAIO Digital, a Connecticut-based tech company, plans a $6 billion data center campus on nearly 300 acres feet from the Ngundues’ property. When completed, the project would span the equivalent of nearly 600 football fields, draw enough electricity to power more than half of all Arkansas households, and use as much as 1 million gallons of fresh water per day.
“The fact that we were not told in the beginning kind of bothers me because you’re in our backyard, literally in our backyard,” Amber Ngundue told Arkansas Times. “It’s like our voices didn’t matter.”
Permit path shifted
When AVAIO first approached the Little Rock District of the Army Corps of Engineers in early 2025, a Corps project manager wrote on March 6, 2025: “After discussing with my boss, a standard permit application will need to be turned in.” A standard permit triggers public notice and a rigorous review for projects with potentially significant impacts to waters of the United States.
That changed after President Trump issued an executive order in July 2025 directing the Environmental Protection Agency and the Army Corps of Engineers to ease Clean Water Act permitting requirements for data center infrastructure, citing national security. AVAIO then pursued a nationwide permit — a streamlined approval with no public notification requirement, typically reserved for minimal-impact projects.
“The nationwide permit is supposed to be minimal impact. This is not going to be a minimal impact to this wetland system,” said Kyla Bennett, former EPA wetlands permit reviewer and science policy director at Public Employees for Environmental Responsibility. “It’s just not.”
In January 2026, the Corps modified its rules to explicitly open nationwide permits to data centers.
National security invoked
In July 2026, a Corps spokesperson declined to answer Arkansas Times questions about AVAIO’s permitting status, writing: “National Security concerns and sensitive business operations preclude us releasing anything at this stage.”
Environmental lawyer Rob Lee said the Corps has a pattern of using national security to conceal details about controversial infrastructure projects. “It’s attempting to pull every string possible to shield information from the public and to try to ram these things through before the public has time to understand what’s happening.”

Members of Arkansas’ congressional delegation intervened. U.S. Sen. John Boozman’s office asked the Corps about the project timeline. A week later, U.S. Sen. Tom Cotton’s office contacted the Corps, asking: “What is your expected timeline for final action?”
Disputed approvals
AVAIO claims it secured the approvals needed to move forward by early August 2026. The Army Corps of Engineers said it was still evaluating the property as of late October, leaving residents what could be a last-ditch opportunity to challenge the project’s environmental impacts and bring it under new county regulations.
India Jackson, whose family owns land across from the project site, said: “They have made us the sacrificial lamb for economic growth. This is a problem for our way of life considering most people in our area farm, fish and hunt.”
On its Little Rock campus page updated January 12, 2026, AVAIO Digital states it has broken ground on the 296-acre Project Leo with a fully approved Site Plan, pre-existing water and sewer connections requiring no upgrades, and an executed energy services agreement with Entergy Arkansas for initial grid capacity energized in Q4 2027.
The company lists Pulaski County Judge Barry Hyde and Governor Sarah Huckabee Sanders endorsing the $6 billion investment as the largest in Arkansas history.
AVAIO Digital Partners, launched in 2021 by infrastructure investment firm AVAIO Capital (founded 2016), broke ground in September 2025 on the 116 MW Taurus Data Center Hub in Brandon, Mississippi, a $6 billion project on 329 acres with Entergy Mississippi power and water-efficient design including rainwater recapture.
The project site sits in the Lorance Creek Focal Area, designated by the Arkansas Natural Heritage Commission for its unique plant and animal life. The Lorance Creek Natural Area, two miles downstream, hosts a cypress-tupelo swamp with 600 plant species and 125 bird species.