PennLive reports that Dauphin County drivers face roughly 15 more years of detours and lane shifts as the I-83 Capital Beltway project pushes toward a 2040 finish line.
The Pennsylvania Department of Transportation is moving into the most disruptive phase yet: a $1.3 billion replacement of the John Harris Memorial Bridge, the highest bid in the agency’s history. A joint venture of Joseph B. Fay Company and New Enterprise Stone & Lime Company submitted the apparent low bid of $1.289 billion, according to PennLive and Local21News.com. Work on the South Bridge is expected to begin in 2027 and run through 2039.
More than 125,000 vehicles cross the 1960 span daily. The plan builds a new northbound bridge south of the existing structure, shifts traffic onto it, then demolishes the old bridge to build the southbound span in its footprint. Simultaneously, PennDOT will reconfigure the Lemoyne interchange, replace the South Third Street bridge in Lemoyne, and reconstruct the viaduct from the river to Route 230 (Cameron Street), including the Front Street/2nd Street interchange.

The master plan dates to 2003. In 2017, PennDOT finished a $104 million phase that widened 2.77 miles from just south of Union Deposit Road to I-81 to three lanes each way. The 29th Street Bridge replacement wrapped up in October 2025 after the original span closed and was demolished in July 2024.
The new bridge carries a sidewalk and shoulder on the west side and a protected shared-use lane for bicycles and pedestrians on the east side behind a 4-foot concrete barrier.
On November 16, the northbound I-83 ramp to 13th Street in Harrisburg closed permanently. PennDOT opened a new Exit 44-A ramp to Route 230 (Cameron Street) with a traffic signal at the intersection. That work is part of East Shore Section 3, due for completion by October 12, 2027. Rolling roadblocks of about 10 minutes each have been running weekdays between noon and 2 p.m. on both directions of I-83 through mid-December for earthwork.
The 19th Street bridge and ramps, closed for about a year, are now on pace to reopen in summer 2027 — roughly six months later than the previous October 2026 estimate. PennDOT is also accelerating Section 2, which runs from just south of the Union Deposit Interchange to 29th Street and includes reconstruction of the Eisenhower Interchange and portions of US 322, I-283 and Eisenhower Boulevard.
I-83 will be widened to three lanes in each direction with new connections to I-283 and US 322, plus updated interchanges at Derry Street and Paxton Street. Bids for the first five Section 2 contracts are scheduled for December 2027, with construction starting in 2028.
The Pennsylvania Department of Transportation was created from the former Department of Highways by Act 120 on May 6, 1970, consolidating transportation functions previously scattered across several state agencies. Today it oversees nearly 40,000 miles of state roads and about 25,400 bridges, a network that includes the I-83 corridor now undergoing its most expensive project ever.
Project details are available on the PennDOT I-83 South Bridge Project page.