Huntsville Building $70M Pinhook Creek Corridor With Skybridge Slated for 2030

The city of Huntsville is building a $70 million Pinhook Creek corridor with flood mitigation, a linear park, and a 1,400-foot Memorial Parkway Skybridge slated for 2030, Wisevoter reported.

More than $50 million in federal grant money backs the project, a sum that requires completion within five years. The grant’s clock effectively sets the 2030 target as a condition of funding rather than an aspiration. Kathy Martin, the city’s senior director of engineering, told AL.com the work is currently on schedule despite an early delay waiting for manufactured blocks.

“We are currently on schedule,” Martin told AL.com. “The contractor has been able to make significant progress.”

The corridor sits amid a cluster of major investments. A $200 million expansion at the Von Braun Center and the $375 million Front Row development along Clinton Avenue are both underway. The Skybridge will link the Clinton Avenue interchange area, the Lowe Mill district, and Seminole Drive, where the $400 million Mill Creek Choice Neighborhood Initiative is taking shape.

Huntsville Building $70M Pinhook Creek Corridor With Skybridge Slated for 2030
Photo: yahoo.com

Martin described four distinct phases to AL.com, each requiring different trades. The first phase channels the creek on the east bank behind the Von Braun Center. Crews started there to avoid conflict with the VBC expansion. By mid-2027, Martin said, the new channel should be visible and the existing railroad bridge behind the VBC should be under demolition.

A new rail bridge will rise concurrently with the channel work. Only after those walls are established will the city bid the cable-suspension Skybridge. That 1,400-foot, 12-foot-wide span over Memorial Parkway and Governors Drive carries a three-year build timeline, with much of the fabrication occurring off-site. Martin expects that work to begin by late 2027.

The final phase installs the linear park — greenway paths, landscaping, irrigation, decorative lighting, benches, and three precast pedestrian bridges connecting to the Von Braun Center, the medical mall, and Lowe Mill.

The federal grant requires a local match, but neither Wisevoter nor AL.com specified how the remaining $20 million is being covered. Martin confirmed the grant’s five-year completion mandate to AL.com, placing the 2030 target inside that window.

The Von Braun Center, an entertainment complex that opened in 1975 as the Von Braun Civic Center and dropped “Civic” from its name in 1997, anchors the corridor’s western edge.

The city is now executing a $200 million expansion there, the latest in a series that added South Hall in 1997, Mars Music Hall and Rhythm on Monroe in 2020, and renovated North Hall in 2023. The complex includes an arena, multiple exhibit halls, a concert hall, and a playhouse.

Construction will continue near Memorial Parkway, the Von Braun Center, and Clinton Avenue. The Skybridge will eventually add a pedestrian crossing over two major thoroughfares, though the city has not released closure or detour details. The next visible milestones arrive mid-2027: a redefined creek channel and the start of railroad bridge demolition.